Annalue Drive & East University Drive Intersection Improvements

Development Services Building
171 N Ross St
-
(334) 501-7390 -
webengineering@auburnal.gov -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview Traffic Transportation & Parking Improvements
This project will bring traffic flow and safety improvements to East University Drive at its intersections with Annalue Drive and Saugahatchee Road. Improvements include the addition of northbound and southbound left turn lanes on East University and new signal poles at the Annalue intersection. A median island will be constructed along East University at the intersection of Saugahatchee Road, creating an intersection that only allows right-in/right-out turns. The portion of Saugahatchee Road stretching from East University to Annalue will be removed to increase safety for travelers of this area. The project is part of the City of Auburn's Comprehensive City-Wide Traffic Study.
The project was completed on Apr 19, 2024 with a total capital budget of $1,189,394.65.
Photos




Timeline
Close Out Finishes
May 19, 2024
Close Out Starts
Apr 20, 2024
Construction Finishes
Apr 19, 2024
Construction Starts
Sep 5, 2023
Contracts Finishes
May 5, 2023
City Council / AWWB Starts
Apr 4, 2023
Contracts Starts
Apr 4, 2023
Bid Opening Starts
Mar 21, 2023
Bid Advertisement Finishes
Mar 21, 2023
Bid Advertisement Starts
Feb 26, 2023
Design Finishes
Apr 30, 2022
Design Starts
Oct 9, 2021