Cox Road and Wire Road Roundabout

Development Services Building
171 N Ross St
-
(334) 501-7390 -
webengineering@auburnal.gov -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview Traffic Transportation & Parking Improvements
This project includes the construction of a roundabout at the intersection of Wire Road and Cox Road to facilitate improved traffic flow through the area.
The project was completed on Sep 16, 2022 with a total capital budget of $2,209,146.10.
Photos




Timeline
Sep 2022
Construction Finishes
Sep 16, 2022
Jul 2021
Contracts Finishes
Jul 5, 2021
Jul 2021
Construction Starts
Jul 5, 2021
Jun 2021
Contracts Starts
Jun 16, 2021
Jun 2021
City Council Starts
Jun 15, 2021
Jun 2021
Bid Opening Starts
Jun 8, 2021
May 2021
Bid advertisement Finishes
May 30, 2021
May 2021
Bid advertisement Starts
May 2, 2021
Feb 2021
ROW/Easement Acquisition Finishes
Feb 1, 2021
Nov 2020
Design w/ final docs - ALDOT Approval Finishes
Nov 30, 2020
Aug 2020
ROW/Easement Acquisition Starts
Aug 31, 2020
Dec 2019
Design w/ final docs - ALDOT Approval Starts
Dec 5, 2019
Jul 2019
ALDOT Review/Design 90% Finishes
Jul 20, 2019
Aug 2018
ALDOT Review/Design 90% Starts
Aug 6, 2018
Jul 2018
Design 60% - Barge Finishes
Jul 18, 2018
Jun 2018
Design 60% - Barge Starts
Jun 14, 2018