Margie Piper Bailey Field Renovations
Project Overview Park Improvements
Renovations at Margie Piper Bailey Field to include adding dirt where needed, replacing sod, repairing irrigation, and adding fencing. The project is part of the City of Auburn's Parks‚ Recreation‚ & Culture Master Plan.
The project was completed on Aug 10, 2023 with a total capital budget of $170,343.00.
Photos




Timeline
Aug 2023
Construction Finishes
Aug 10, 2023
Aug 2023
Close Out Starts
Aug 7, 2023
Feb 2023
Construction Starts
Feb 1, 2023
Dec 2022
Contracts Finishes
Dec 28, 2022
Dec 2022
Contracts Starts
Dec 9, 2022
Dec 2022
Bid Opening Starts
Dec 8, 2022
Dec 2022
City Council / AWWB Starts
Dec 8, 2022
Dec 2022
Bid Advertisement Finishes
Dec 8, 2022
Nov 2022
Bid Advertisement Starts
Nov 19, 2022
Nov 2022
Design Finishes
Nov 18, 2022
Sep 2022
Design Starts
Sep 30, 2022