Martin Luther King Drive Multi-Use Path (ALDOT TAP)

Development Services Building
171 N Ross St
-
(334) 501-7390 -
webengineering@auburnal.gov -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview Sidewalks Streetlights & Streetscapes
This project will increase the walkability of one of the main gateways into Auburn, linking up with an adjacent project, the MLK Streetscape Project, to produce a path stretching two miles into the City. This will allow pedestrians and cyclists to travel safely from Martin Luther King Drive to downtown and campus. The project is part of the City of Auburn's Northwest Auburn Neighborhood Plan.
The project was completed on Apr 28, 2023 with a total capital budget of $813,214.65.
Photos




Timeline
Apr 2023
Construction Finishes
Apr 28, 2023
Apr 2022
Construction Starts
Apr 11, 2022
Mar 2022
Contracts Finishes
Mar 16, 2022
Feb 2022
Contracts Starts
Feb 16, 2022
Feb 2022
City Council Starts
Feb 15, 2022
Feb 2022
Bid Advertisement Finishes
Feb 1, 2022
Feb 2022
Bid Opening Starts
Feb 1, 2022
Jan 2022
Bid Advertisement Starts
Jan 9, 2022
Nov 2021
ALDOT Review Finishes
Nov 26, 2021
Apr 2020
Design Finishes
Apr 28, 2020
Sep 2019
Easement Acquisition Finishes
Sep 15, 2019
Jul 2019
Easement Acquisition Starts
Jul 2, 2019
Apr 2019
ALDOT Review Starts
Apr 1, 2019
Sep 2018
Design Starts
Sep 11, 2018