Design sidewalk on Longleaf Drive from Donahue Drive to South College by September 30, 2008.
Design sidewalk on Gay Street from Halal Court to Shelton Mill Road by September 30, 2008.
Design sidewalk on Gatewood Drive from Academy Drive to end by September 30, 2008.
Continue to rebuild/repair an estimated 750 feet of broken sidewalk by September 30, 2008.
Improve storm sewer infrastructure, including ditch maintenance and piping projects, by completing at least two miles of stream
maintenance by September 30, 2008.
Perform crack-sealing on 10 miles of streets by September 30, 2008.
Complete FY 08 Streets Resurfacing Project by September 30, 2008.
Traffic Engineering Division
Design a multiuse path on South Donahue Drive from South College Street to East University Drive by September 2008.
Design intersection improvements to enhance traffic flow and reduce accidents at Donahue Drive and West Magnolia Avenue by July
2008.
Design intersection improvements to enhance traffic flow and reduce accidents at South College Street and East University
Drive/Shug Jordan Drive by July 2008.
Design intersection improvements to enhance traffic flow and reduce accidents at East University Drive and Shelton Mill Road by
September 2008.
Install traffic signals at East Samford Avenue and East Glenn Avenue when Samford Avenue is extended by September 2008.
Install traffic signals at East Samford Avenue and East University Drive when Samford Avenue is extended by September 2008.
Perform signal warrant analysis for a traffic signal at Willow Creek Road and Hwy 14 by September 2008.
Perform signal warrant analysis for a traffic signal at Opelika Road and Saugahatchee Road upon substantial completion of
subdivision by September 2008.
Improve access to critical data by continuously updating traffic counts in GIS to within 5 years by September 2008.
Complete ALDOT/FHWA required Bridge Inspections by June 2008.
Complete analysis of Intelligent Transportation Systems applications for City of Auburn by September 2008.
Engineering Division
Design and construct the Samford Avenue Extension from East University Drive to Glenn Avenue by September 2008.
Design replacement of Wire Road Bridge by August 2008.
Design the East Glenn Avenue Median Project by September 2008.
Design project to widen Bragg Avenue to three lanes by September 2008.
Design project to improve drainage on Opelika Road near Guthries by August 2008.
Design sidewalk on West Glenn Avenue from Byrd Street to Donahue Drive by September 2008 (CDBG).
Complete annual update of Engineering Standard Operating Procedures by June 2008.
Inspections Division
Conduct annual detention pond inspections by September 2008.
Have all the inspectors certified/recertified as Grade I Water Treatment Operator and Roadway Technician by September 2008.
Complete FY 08 Streets Re-striping Project by September 2008.
Oversee construction of the addition to the Library by September 2008.
Oversee construction of the Samford Avenue Extension project by September 2008.
Administrative Division Goals
Complete wetlands bank study by September 2008.
Complete development of a comprehensive Engineering Manual that consolidates all current design standards and specifications
and incorporates new specifications into one easy to use source for use by the Engineering staff as well as the development community
by September 2008.