In order for the applicant's plans to be reviewed at the weekly meeting, the applicant
must submit the required number of copies of all plans and all other required documents
to the Public Works Department's Plans Review Engineer at least twenty-two (22)
days before the regularly scheduled meeting at which time the plans are to undergo
final review. The applicant will receive, within fifteen (15) days of the submittal
deadline, from the City of Auburn via e-mail, a detailed list of all comments concerning
the submitted documents. This will give the applicant six (6) days to address the
comments before appearing before the DRT where the applicant will be asked to address
each comment.
If, at the first meeting, all comments are addressed to the satisfaction of the
DRT then the applicant will receive final Approval at that time. If the applicant
has not addressed all comments to the satisfaction of the DRT, then three other
actions are possible: (1) Conditional Approval - A conditional approval may be granted
in cases where the remaining issues are few and will not require substantial review
time. (2) Continuance - A continuance may be granted (or requested by the applicant)
when there are more than a few outstanding issues and/or the outstanding issues
are significant in nature. A continuance may be to a date certain but not to exceed
three weeks from the date of the initial meeting. (3) Denial - A denial may be issued
in situations where outstanding issues are very significant and will require a substantial
amount of review time by staff. A denial will also be issued if by the 4th week
(three weeks after the initial meeting) an Approval or Conditional Approval has
not been granted. If a denial is issued, the applicant must resubmit to the DRT
and restart the process, including repayment of applicable fees.
All submittals by the applicant shall be accompanied by the appropriate fees as
set forth in the DRT Schedule of Fees and shall meet the criteria set forth for
site plans in Article VIII of the City of Auburn Zoning Ordinance as well as the
criteria set forth for Engineering/Construction Plans in Article III of the City
of Auburn Subdivision Regulations. Submittal requirements are outlined on the DRT
Application as well as the engineering and planning checklists.
| Submittal | Fee |
| Site Plans | $75.00 |
| Subdivison Plans | TBD |
2010 DRT Calendar
2009 DRT Calendar
Site DRT Application Form
Subdivision
DRT Application Form
Submittal Requirements
Meeting Waiver
Engineering Site Plans Checklist
Engineering Subdivision Plans Checklist
Planning Site Plan Checklist
Design Standards Clarification
Memo & Sediment Worksheet
DRT Process Flow Chart